|
Activity # |
Status |
|
GENERAL: |
| 1 |
Oral Health
- An internal team is presently reviewing the ERHA’s draft
decentralization plan. The Plan to be finalized by May 21, 2001.
- Outreach program targeted for commencement in September 2001 in the
Nariva/Mayaro and St. Andrew/St. David districts. Vehicles are being
procured and staff recruitment finalized.
- Client screening commenced in quarter. Actual procedures with a health
promotion focus are scheduled to begin in September 2001.
|
| 2 |
Ambulance Services
- EHS established at the four stations that include: Sangre Grande
Hospital, Mayaro, Rio Claro and Toco. The system is performing
satisfactorily.
|
| 3 |
User Fees
- The various user fee initiatives (previous) are producing favorable
returns.
- New fee-based initiatives added and performing satisfactorily to date.
These include Bronchoscopy and PHI inspection of off-shore platforms.
|
| 4 |
Radiology
- Introduction of new services on hold. Awaiting completion of the "new"
GP wing at the Rio Claro Health Facility.
- Equipment and other arrangements relative to implementation already in
place.
|
| 5 |
GP Services
- Introduction of the new GP services on hold in Toco pending completion
of the Toco Health Centre. Other activities relative to implementation
such as additional staff recruitment are in progress.
|
| 6 |
Cervical Cancer
Screening
- Staff training issues still being ironed out. The ERHA team is working
along with Dr. Swantson and Ms. Granderson of the Microbiology Department,
UWI.
- Efforts being made to commence the service in the third/fourth quarter
given the various constraints.
|
| 7 |
Baby Friendly
- Coordinating and Monitoring Teams have been meeting regularly.
Training of staff and community personnel is in progress. Plans are on
target to facilitate baby friendly certification in October/November 2001.
|
| 8 |
Lab Services
- Microbiology services introduced in April 2001 as planned.
- Equipment required for the introduction of the Biochemistry services
are being procured. Consumables and reagents are already in stock.
|
| 9 |
Health Management
- Letter of offer issued to preferred candidate. Awaiting response.
|
| 10 |
Primary Care Model
- Action on this project was deferred pending outcome of the Primary
Care Consultancy due to commence shortly by the Ministry.
|
| 11 |
Chronic Disease
- Action plan developed and being executed. Pilot project launch
scheduled for August 1, 2001.
|
| 12 |
Adolescent Health
- No progress. To be reviewed in the next quarter.
|
| 13 |
PHCIDP
- Very slow progress on the various projects owing partly to tardy
payment patterns by PAU. Issue has been raised at various levels at the Ministry of Health.
- There are indications from the Ministry that some contracts that were
scheduled to commence this year such as Valencia and Coryal may be delayed
for as much as two years.
- Expected completion dates for projects already in progress:
- - Cumana May 31, 2001
- - Toco June 30, 2001
- - Rio Claro July 17, 2001
- - Matelot June 30, 2001
- - Grand Riviere June 30, 2001
- - Matura June 30, 2001
-
-
Biche June 30, 2001
- - Brothers Road June 30th 2001
|
| 14 |
Sangre Grande
Enhanced Health Centre / Sangre Grande Development Control Plan
- Consultant’s contract was amended to integrate both projects. No
further development since.
|
| 15 |
Medical Equipment
- Equipment being received for Toco, Cumana and Rio Claro Health
Centres. Tenders to be issued by PAU for other outstanding pieces of
equipment..
|
| 16 |
Nurses Quarters
- Funding options did not materialize. Meanwhile, minor works being
done at the Cumana Quarters.
|
| 17 |
Extended Care Unit
- The Project Manager is presently preparing the Scope of Works.
|
| 18 |
Power Generator –
SFGH
- Preventative Maintenance contract awarded.
|
| 19 |
IS/IT
- Some equipment procured under the recurrent budget.
- Non PSIP funding did not materialize.
- Authority represented on MOH committee by Systems Analyst.
|
| 20 |
Public Board
Meeting
- Organizing team has been meeting. The PBM scheduled to be held on June
28, 2001 in Rio Claro.
|
| 21 |
Staff Activities
- Staff Annual General Meeting held on December 13, 2000 as planned.
- Annual Sports and Family Day scheduled for August 2001.
|
| 22 |
Home Care Nursing
Priority given to Chronic Disease Pilot Project. Home Care Nursing
being reviewed.
|
| 23 |
Health Promotion
- Restructure of Health Education section to be pursued following
appointment of the Health Promotion Specialist.
- Health Promotion Month Planning Committee in place. Plans in place for
execution of April/May 2001 health promotion activities. Focus this year
on Men’s Health.
|
| 24 |
Nursing Management
- Advertisements published re vacancy for Nursing Manager. Unsuitable
applicants. Deferred
Until
further notice.
|
| 25 |
Mental Health
Services
- Meeting scheduled for May 2001 with Ministry. Due to discuss the
Authority’s role and expectations re service delivery.
|
| |
FINANCE & ACCOUNTING |
| 1 |
Accounts Department
- Board-approved departmental structure implemented in January 2001 as
planned.
|
| 2 |
Region-wide
Accounting Operations
- The F&A department is engaged in discussions with MMS Consultants on
the subject.
|
| 3 |
Cash Management
- The Roynet Electronic Banking System was installed in December 2000 as
planned.
|
| 4 |
Purchasing System
- A draft plan has been prepared aimed at restructuring the existing
purchasing system. The merits of same being discussed with relevant
personnel.
|
| 5 |
Motor Vehicle Loans
Completed draft with ERHA motor vehicle application forms.
Consultations ongoing with the Comptroller of Accounts and VAT officials
on the subject.
|
| |
HUMAN
RESOURCES: |
| 1 |
Recruitment
- Thirty persons recruited over the period. Recruitment efforts continue
to fill the other key vacancies.
- Working with the MOH re addressing critical shortage of certain
categories of medical personnel.
|
| 2 |
Policies
- The Ministry of Health has adopted an approach of standardization of
policies among the RHA’s. A two-day workshop was held re development of
Human Resource Policies. Other sessions are being arranged.
|
| 3 |
Training
|
| 4 |
Staff Database
- Awaiting IS/IT Manager and Ernst & Young Consultancy. The Ministry is
in the process of recruiting an IS/IT Manager. In the meantime ERHA
employees data maintained under Access software.
|
| 5 |
Pension Plan
|
| 6 |
ERHA Training
Facilities
- Renovations to the LRC to begin in third quarter.
|
| |
QUALITY |
| 1 |
Quality Management
System
- Risk Management Protocol developed for testing at the SGH.
- Training proposal in support of the Quality Improvement System
submitted to PAHO and approval received to conduct training in May 2001.
- Two officers of the Quality department have been assigned to the
Standards and Protocol Committee function respectively. A full committee
is yet to be established. The Accreditation core committee is expected to
be formed by May 31, 2001.
|
| 2 |
Quality Improvement
System
- Training for quality team leaders scheduled for May 2001. Improvement
projects to be agreed at training forum.
|
| 3 |
Waiting Times
- Strategies being developed for sustainable improvements.
|
| 4 |
Customer Relations
System
- The Customer Relations System at the SGH now fully established and
functioning satisfactorily.
- System for community services constrained by absence of the Quality
Coordinator.
|
| 5 |
Risk Management
- First phase (Sensitization) completed at the SGH.
- Draft Assessment Protocol prepared for piloting. To form part of the
Risk Management Consultancy.
|
| 6 |
Accreditation
- RHA’s core committee established. Consultancy dates revised to April
2001.
|
| 7 |
Awards System
|
| 8 |
PEP Policy
- System implemented partially at the SGH and MDH.
- Implementation of the community services system outstanding.
- Reporting cycle to be finalized. Target dates to be revised but to
ensure implementation by June 30, 2001.
|
| 9 |
TQM Training
- In-house training conducted.
- Awaiting start of the national programme that would facilitate
training for all RHAs. Ministry to issue
tenders
for same.
|
| |
NURSING |
| 1 |
Community Liaision
Unit
- The National Standards and Protocol Committee presently preparing a
discharge planning policy.
- The Ministry’s Policy and Planning Directorate is scheduled to conduct
an impact assessment of the CLU.
|
| 2 |
Nursing Models of
Care
|
| 3 |
Nursing Research
Protocol
- National Nursing Research Officer appointed. National Protocol to be
established.
|
| 4 |
Home Nursing Care
- Target date to be revised.
|
| 5 |
Nursing Staff
Shortage
- Needs assessment document that includes recommendation on the way
forward is being prepared.
|
| 6 |
Health Promotion
|
| 7 |
Clinical Path
- To be incorporated as part of the Accreditation consultancy work.
|
| |
NARIVA /MAYARO: |
| 1 |
Immunization
Programme
- Polio : 17% out of 20%
- MMR/YP: 33% out of 25%
- HIB: 17% out of 20%
|
| 2 |
HIV
- All health centers in the Nariva / Mayaro area participating in the
HIV perinatal transmission reduction program.
- Actual uptake by clients to be determined.
|
| 3 |
Maternal Health
- Cervical Cancer Screening : awaiting development of cytology services
at SGH. Being done at the
Rio Claro Health centre, facilitated by the FPA.
|
| 4 |
Rio Claro Maternity
Unit
- The Unit is presently being renovated. Consultation being held with
Ministry to determine way forward.
|
| 5 |
Child Health
- The baby friendly initiative is in its early stages of implementation
at the various Health Centres.
|
| 6 |
Communicable
Disease
- All Doctors and Institutions are reporting weekly.
- All cases notified by TPHL and IVCD have been investigated and
followed up.
|
| 7 |
Chronic Disease
- (see item #11 under "General")
|
| 8 |
Oral Health
- Plan finalized. Preliminary ground work being done at the schools.
|
| 9 (noted
as item 12 in the Action Plan) |
Infrastructure -
MDH
- Installation of new radiology unit at the MDH: in progress.
- Minor operating theatre :relocated as planned.
|
| |
ST. ANDREW/ST. DAVID: |
| 1 |
Child Health /
Immunization
- Baby friendly initiative at early stages of implementation at various
Health Centres.
Immunization Program ongoing. Polio 49%, DPT: 50%, MMR: 66%, YF: 66%,
HIB: 48%
|
| 2 |
Maternal Health
- Anaemia in pregnancy
- Teenage pregnancy
- Cervical Screening: training for staff in progress. One session done
at SGH. Ongoing training at Mt. Hope.
- Baby Friendly: positive results from the communities. 30% of mothers
solely breast feeding for first three months. 80% Nursing Staff attended
Lactation Management program.
- Births for St. Andrew/St. David: Total = 520, Still births =3, Total
deliveries = 11
|
| 3 |
Chronic Disease
- A detail equipment list prepared. (see also item #11 under "General")
|
| 4 |
Adolescent
Health
- Workshops on HIV/AIDS conducted in secondary schools at Valencia,
Matura, Toco and Manzanilla. A total of 246 students participated.
- Two community adolescent groups established in Toco and Coryal
respectively.
- Monthly meetings continue with Youth Health Committee.
|
| 5 |
Oral Health
- (see item #1 in "General" section)
- 1650 food handlers registered. 442 approved.
- 235 Itinerant Vendors Kitchen inspected.
- 69 Schools inspected.
- 397 kg of animals slaughtered. 60kg meat condemned.
- 24 reports of communicable disease. 100% of the reports investigated.
|
| 7 |
Disaster
Preparedness
- Staff participated in workshop sessions facilities facilitated by NEMA.
|
| 8 |
Disease
Surveillance |
| 9 |
Health Promotion
- The 4 Diabetic support groups continue with monthly meetings. New
group to be established at Cumuto Health Centre.
- All Well-weight management programs re started in March 2001 after a
three months break. Current funding from PAHO sufficient to cover up to
March 2001. Awaiting feedback re "New" proposal submitted for funding for
program for period April 2001 to December 2001.
- Reported increase of members engaged in physical activity.
|
| 10 |
Infrastructure
- (See item 313 in "GeneraI" section for status on the PHCIDP projects).
- Cumana Health Centre Services temporarily transferred to Toco Health
Centre. Patients are being transported to Toco via ERHA shuttle service,
with the exception of Thursdays when a Maxi Taxi is used.
- Clinical services at Toco Health centre transferred to the Maternity
Unit.
- Grand Riviere Health Centre Clinical services transferred to Sans Souci
Health Centre.
ERHA
shuttle
service transports patients temporarily on Thursdays.
- Matelot Health Centre Clinical services temporarily relocated to the
Matura Community Centre.
|
| 11 |
GP Services
|
| 12 |
Quantification of
Arrears re Increment for Public Servants 1987-1995 75% worksheets have been audited. |
| 13 |
Re-introduction of
Incremental Credits to Public Servants
Staff reports forwarded to the Permanent Secretary for approval. |
|
Activity # |
Status |
| 1 |
Surgery
- No Infrastructure work undertaken
|
| 2 |
Medical Records
- Space identified for the storage of inactive medical records.
Refurbishment work to be undertaken.
- Awaiting appointment of Medical Records Officer to pursue
establishment of structure and career path for Medical Records Department.
Also to collaborate with HR re formulation of job descriptions.
|
| 3 |
Infrastructure
- Repairs to service drip stands and trolleys : Completed.
- Provision of additional seating accommodation for visitors outside
wards and in Out Patient Clinic: Completed.
- Replacement for defective louver frames and missing louver blades on
wards : 80% completed. Short louver frames being acquired to finish the
work.
- Installation of wall fans on wards: Completed.
|
| 4 |
Laboratory Services
- (See item #8 in "General" section).
|
| 5 |
IT
- Computer for Internet Service procured and installed at library.
Awaiting printer from supplier. Also awaiting TSTT to install Internet
system at library.
- Two printers procured and installed in the Accounts and Ultra Sound
Services respectively.
|
| 6 |
Policy
- Policy re maintenance of Drip Stands, Trolleys and Wheel Chairs: To be
determined.
|